Release 1.11

  • Feature 7502: Actual start and end time of POs - When starting to work on a PO in SFC, the actual start time is sent back to Optinex and updates the PO. A new estimated end time is calculated using the duration of the PO. Once the PO is completed in SFC, also this time is reported as actual end time to Optinex and updates the PO.
  • Feature 7228: Forecast orders - A new demand type called "Forecast Order" is introduced. Using the same API as for the demand, a forecast order can be sent to Optinex.
  • Feature 7119: Improvements to stock reconciliation - Stock reconciliation, introduced in PI 1.10 has been updated with some smaller improvements.
  • Feature 7577: AoT performance - The performance and usability of the AoT view in Operational Optinex has been improved.
  • Feature 4282: Optimize Gluelam Sequence - Various improvements to the Optimize Gluelam Sequence functionality (latest production date, consider already planned POs, overlap lamella planer and gluepress, consider breaks and deviations).
  • Feature 6559: Demand Info Modal - In the AoT view as well as when creating POs from a demand the detailled information for that specific demand can be accessed clicking on the hyperlink (AoT) or the dedicated button (PO).
  • Feature 6496: Trigger PO-sequence using Create Demand function - When adding a demand for a gluelam product, the PO-sequence can be created directly when creating the demand.
  • Feature 6540: Trigger Forecast log stock from UI - The calculations connected to the log forecasts can be triggered by the user in Optinex.
  • Feature 7859: Auto Scheduler - New functionality introduced in the timeline view to reschedule POs (perfect fitting keeping the sequence of th POs) for the selected machine.
  • User Story 7786: Updated calendar - It is now possible to select week or month view for the calendar.
  • User Story 7811: Updated timeline - It is now possible to select week or month view for the timeline.
  • User Story 5808: Stock forecast in create production order window - When creating a production order all of the forecast values for the included materials are shown for the selected day.
  • User Story 6498: Time resolution in create production order window - When creating a production order it is now possible to select the desired time resolution for the calendar view on the right hand side.
  • User Story 3765: Width, thickness, length & quality in production orders - When creating production orders, the dimension and quality information is populated for the main product.
  • User Story 6557: Custom planner instructions: Customizable planner instructions are introduced. Instruction fields can be defined and mapped to a specific machine. When creating POs for that machine, the instruction field is populated in the PO and can be filled with the needed instructions.
  • User Story 6558: Width, thickness, length & quality in demand grid - The dimension and quality data is shown for each demand in the demand view in Operational Optinex.
  • User Story 1559: New columns to beam view - Updated beam view in Gluelam Optinex with additional columns to show more details for the produced Gluelam beams.
  • User Story 7784: Show week in create PO view - When creating a PO there is the option to switch from the day view to a week view in order to see the calendar of the whole week.
  • User Story 6482: New units in AoT - New special units of measurement can be defined for the resources and selected in AoT view.
  • User Story 7689: European date format - The date formats have been unified showing european date format (day / month / year).
  • User Story 6514: Automate query in AoT - When entering the AoT, the query of the data for the preselected material group is triggered immediately. When then changing the material group, the query is triggered without having to click on "Query".
  • User Story 8094: Show additional instructions in AoT details - For POs with additioal customized planner instructions, a button in the AoT details will allow to see them without having to enter the PO.
  • User story 5934: Possibility to deactivate entity models - Entity models can be set to inactive state in order for Optinex not to consider them.
  • User Story 8085: Comments for weight factor sliders for Optimize Gluelam Sequence - Explanations / information have been added to the sliders used in the Optimizer for the Gluelam Sequences.
  • User Story 7034: Increased Instruction text box - Inside the PO view, the size of the instruction text box has been increased.
  • User Story 8043: APIs for schedule and deviation - Two new APIs for schedule and deviation have been introduced.
  • Bug 2014: Update glue plan card when saving - When saving a glue plan, the glue plan card on the top of the Gluelam Planning view is updated with the correct number of beams in it.
  • Bug 6772: Include test piece in length calculation - The manually added test pieces are considered in the length calculation of a glue set.
  • Bug 7643: Problem with bulk update for state change to closed - Using the bulk update for completed POs to put them in closed state now works as it should.
  • Bug 6141: Status of copied POs - Whenever a PO is copied, the newly created PO is set to state preview, regardless of what state the original PO is in.
  • Bug 7081: Event log not updating when using bulk edit - When using the bulk edit functionality to update the state of one or more POs, the event log for the state change is created correctly.
  • Bug 7227: Issue with schedules - When changing week or month in timeline or calendar view, the correct schedules are shown highlighted in green color.
  • Bug 7446: Max stock issue with number higher then 999 - Max stock level can now be set to any number, also higher then 999.
  • Bug 5746: Issue with schedules when there are more machines to a machine group - The schedule for a machine in timeline and calendar view is not displayed for the whole machine group but for each of the single machines in the machine group.
  • Bug 5801: Removed grid header filters - In the create schedule window, the filtering possibility on the grid headers has been removed as they are not needed.
  • Bug 8174: Date format in Forecast call - Depending on the location and browser settings, different date formats created problems in some of the API calls and are fixed now.
  • Bug 8023: Context menu over deviations - In calendar and timeline view when clicking on a deviation, the context menu shown for POs (copy / edit / delete) will not be shown for deviations.
  • Bug 7675: Print One in Gluelam not loading correctly - Data issue while loading Print One for large Glue Plans solved.
  • User Story 7094: Remember selected language - Once a language is selected for SFC, the app will remember the selection for the next time using it.
  • User Story 7241: Naming of material - Instead of the material code the material description is used for the materials in a PO.
  • User Story 7679: Send POs back to planned state - The state of released POs can be changed to planned from the SFC app.
  • User Story 7582: Operator comments - Introduce comment field for operators using the SFC app. The comment will be shown in the PO in Optinex.