Testing Procedure
The diagram below shows the general release cycle for Optinex. A product increment contains 3 sprints, each sprint 3 weeks long.
At the end of a product increment, a new release candidate is created, and after quality is assured by ForestX and customer testing, it is pushed to the production environment.
Below is also a table with the actual release plan for the upcoming Product Increments.
gantt
title Optinex iterative product development process
dateFormat YYYY-MM-DD
todayMarker off
section Product Increment 1 (9 Weeks)
Sprint 1 (week 1-3) :s1, 2000-01-02, 21d
Sprint 2 (week 4-6) :s2, 2000-01-23, 21d
Sprint 3 (week 7-9) :s3, 2000-02-13, 21d
Regression Testing FX (week 9-10) :rt, 2000-02-27, 14d
Customer Testing (week 10) :ct, 2000-03-05, 7d
Push to Production (week 11) :milestone, 2000-03-15, 0d
section Product Increment 2 (9 Weeks)
Sprint 1 (week 10-12) :s1-2, 2000-03-05, 21d
Sprint 2 (week 13-15) :s2-2, 2000-03-26, 21d
Sprint 3 (week 16-18) :s3-2, 2000-04-16, 21d
Regression Testing FX(week 18-19) :rt-2, 2000-05-07, 14d
Customer Testing (week 19) :ct-2, 2000-05-14, 7d
Push to Production (week 20) :milestone, 2000-05-24, 0d
Product Increment | Regression Testing FX | Customer Testing | Push to Production | Status | Comments |
---|---|---|---|---|---|
PI 19 | W42-W43 | W43 | W44 / W45 | Complete | |
PI 20 | W49-W50 | W50 | W50 / W51 | Complete | Live on 25/01/09 |
PI 21 | W8-W9 | W9 | W9 / W10 | Complete | Live on 25/03/26 |
PI 22 | W17-W18 | W18 | W18 / W19 | Complete | Live on 25/05/19 |
PI 23 | W26-W27 | W27 | W28 / W29 | Complete | Live on 25/07/17 |
PI 24 | W35-W36 | W36 | W37 / W38 | Ongoing |