Testing Procedure

The diagram below shows the general release cycle for Optinex. A product increment contains 3 sprints, each sprint 3 weeks long.
At the end of a product increment, a new release candidate is created, and after quality is assured by ForestX and customer testing, it is pushed to the production environment.

Below is also a table with the actual release plan for the upcoming Product Increments.

gantt
    title Optinex iterative product development process
    dateFormat  YYYY-MM-DD
    todayMarker off

    section Product Increment 1 (9 Weeks)
    Sprint 1 (week 1-3)          :s1, 2000-01-02, 21d
    Sprint 2 (week 4-6)          :s2, 2000-01-23, 21d
    Sprint 3 (week 7-9)          :s3, 2000-02-13, 21d
    Regression Testing FX (week 9-10) :rt, 2000-02-27, 14d
    Customer Testing (week 10)        :ct, 2000-03-05, 7d
    Push to Production (week 11)      :milestone, 2000-03-15, 0d

    section Product Increment 2 (9 Weeks)
    Sprint 1 (week 10-12)        :s1-2, 2000-03-05, 21d
    Sprint 2 (week 13-15)        :s2-2, 2000-03-26, 21d
    Sprint 3 (week 16-18)        :s3-2, 2000-04-16, 21d
    Regression Testing FX(week 18-19) :rt-2, 2000-05-07, 14d
    Customer Testing (week 19)        :ct-2, 2000-05-14, 7d
    Push to Production (week 20)      :milestone, 2000-05-24, 0d


Product Increment Regression Testing FX Customer Testing Push to Production Status Comments
PI 19 W42-W43 W43 W44 / W45 Complete
PI 20 W49-W50 W50 W50 / W51 Complete Live on 25/01/09
PI 21 W8-W9 W9 W9 / W10 Complete Live on 25/03/26
PI 22 W17-W18 W18 W18 / W19 Complete Live on 25/05/19
PI 23 W26-W27 W27 W28 / W29 Complete Live on 25/07/17
PI 24 W35-W36 W36 W37 / W38 Ongoing